Project Information
Project Name | Transmission Line Substation 132 Kv | Status | Active |
---|---|---|---|
Region | Arab countries | Country | Yemen |
Sector | Energy | Sub Sector | Education |
Technical Details:
Project Objectives | THE PROJECT AIMS AT RE-ENFORCING AND EXTENDING THE ELECTRIC TRANSMISSION IN YEMEN TO FURTHER THE ACCESS TO ELECTRIC POWER TO THE RURAL AREAS IN A SUSTANABLE MANNER. |
---|---|
Project Description | THE PROJECT CONSISTS OF THE SUPPLY AND INSTALLATION OF A 132 KV TRANSMISSION LINE TO CONNECT THE TOWNS OF YAFAA AND AL-BAIDHA TO THE NATIONAL POWER GRID AT HABEELEIN AND OF THE EXPANSION AND REHABILITATION OF THE MIDIUM AND LOW VOLTAGE DISTRIBUTION NETWORKS IN THE RURAL AREAS OF YAFAA AND HABEELEIN CAPABLE OF MEETING A DEMAND OF UP TO 180 MVA. |
Estimated Cost | 262.00 Million Dollars |
Financing :
Co Financiers | |||
---|---|---|---|
Kuwait Fund Financing | |||
Type | Loan | No. | 847 |
Amount | 9,000,000 KD | Effective Date | 15-08-2012 |
Implementing Agency :
Agency | PUBLIC ELECTRICITY C0RPORATION | ypecnt@y.net.ye | |
---|---|---|---|
Address 1 | AIRPORT STREET P.O.BOX 178 SANAA YEMEN | Fax No | 009671 328150-1 |
Address 2 | ** | Telephone No | 009671 328141-2-3 |
Consultant/s:
Status | - |
---|
Contractor/s:
Status | Not Appointed |
---|
Progress:
Technical Progress | Delayed | ||
---|---|---|---|
Financial Progress | 0.00% | ||
Expected Completion Date | 12-2021 | ||
Created | 05-12-2010 | Updated | 16-08-2020 |