Project Name | Rehabilitation Of Al-jeiah And Al-zouk Power Station | Status | Cancelled |
---|---|---|---|
Region | Arab countries | Country | Lebanon |
Sector | Energy | Sub Sector | Exchanges |
Technical Details:
Project Objectives | Meeting part of demand and improve reliability and availability of electric energy supply |
---|---|
Project Description | Rehabilitation works of 5 generation units at Al- Jeiah with capacity 330mw and 4 generation units with capacity 600mwAl-Zouk power stations |
Estimated Cost | 445.00 Million Dollars |
Financing :
Co Financiers | |||
---|---|---|---|
Kuwait Fund Financing | |||
Type | Loan | No. | 861 |
Amount | Effective Date |
Implementing Agency :
Agency | CDR and the Ministry of Energy and Water | 1 | |
---|---|---|---|
Address 1 | 1 | Fax No | 1 |
Address 2 | 1 | Telephone No | 1 |
Consultant/s:
Status | Not Appointed |
---|
Contractor/s:
Status | Not Appointed |
---|
Progress:
Technical Progress | Good | ||
---|---|---|---|
Financial Progress | 0.00% | ||
Expected Completion Date | 12-2016 | ||
Created | 06-03-2012 | Updated | 22-06-2017 |