Project Name | Assiut Steam Power Station | Status | Active |
---|---|---|---|
Region | Arab countries | Country | Egypt |
Sector | Energy | Sub Sector | Exchanges |
Technical Details:
Project Objectives | THE PURPOSE OF THE PROJECT IS TO HELP MEET THE GROWING DEMAND ON POWER IN EGYPT. |
---|---|
Project Description | THE PROJECT CONSISTS OF THE CONSTRUCTION,SUPPLY AND INSTALLATION OF A COMBINED CYCLE POWER PLANT AT BANHA COMPRISING 2X250 MW COMBUSTION TURBINES AND 1X650 MW STEAM UNIT. THE PLANT WILL USE HEAVY FUEL OIL AS BASE FULE AND NATURAL GAS AS STAND BY. |
Estimated Cost | 780.00 Million Dollars |
Financing :
Co Financiers | |||
---|---|---|---|
Kuwait Fund Financing | |||
Type | Loan | No. | 892 |
Amount | 24,008,955 KD | Effective Date | 19-10-2014 |
Implementing Agency :
Agency | POWER | ** | |
---|---|---|---|
Address 1 | ASSUIT | Fax No | ** |
Address 2 | EGYPT | Telephone No | ** |
Consultant/s:
Status | Appointed |
---|
Contractor/s:
Status | Not Appointed |
---|
Progress:
Technical Progress | Fair | ||
---|---|---|---|
Financial Progress | 100.00% | ||
Expected Completion Date | 06-2020 | ||