Project Name | Construction Of Electrical Thermal Power Plant | Status | Active |
---|---|---|---|
Region | Arab countries | Country | Djibouti |
Sector | Energy | Sub Sector | Exchanges |
Technical Details:
Project Objectives | meeting portion of the electricity demand by utilizing thermal geothermal energy available in Djibouti |
---|---|
Project Description | the projects consists of developing a geothermal power plant with capacity about 15 MW with facilities to connect to the national grid |
Estimated Cost | 22.00 Million Dollars |
Financing :
Co Financiers | |||
---|---|---|---|
Kuwait Fund Financing | |||
Type | Loan | No. | 991 |
Amount | 8,000,000 KD | Effective Date | 05-02-2020 |
Implementing Agency :
Agency | ODDEG | oddegdirection@gmail.com | |
---|---|---|---|
Address 1 | Presidency of the Republic Route Nationale 1, Zone Industrielle PK20 | Fax No | N |
Address 2 | 2 | Telephone No | 00253-21 31 51 00 |
Consultant/s:
Status | Not Appointed |
---|
Contractor/s:
Status | Not Appointed |
---|
Progress:
Technical Progress | Poor | ||
---|---|---|---|
Financial Progress | 0.00% | ||
Expected Completion Date | 12-2021 | ||
Created | 07-09-2017 | Updated | 16-08-2020 |