Project Information
Project Name | Golen Gol Hydropowe/supplementry Loan | Status | Active |
---|---|---|---|
Region | East, south asia & the pacific countries | Country | Pakistan |
Sector | Energy | Sub Sector | Exchanges |
Technical Details:
Project Objectives | The project aims to meet the demand for electrical energy in the North-West Frontier Province, about 22 km from the city of Chitral, by developing hydroelectric power. |
---|---|
Project Description | The project includes building a dam on the Golan Gol River, about 1 km upstream from the village of Babuka, and an open channel and tunnel to change the course of the river for the electrical generating station. The project also includes the construction, supply, installation and testing of three hydroelectric generating units and their accessories, in addition to the construction, supply, installation and testing of a 132 kV electricity transmission line. To connect the generating station to the national grid. |
Estimated Cost | 214.00 Million Dollars |
Financing :
Co Financiers | |||
---|---|---|---|
Kuwait Fund Financing | |||
Type | Loan | No. | 993 |
Amount | 4,500,000 KD | Effective Date | 14-06-2018 |
Implementing Agency :
Agency | WAPDA HYDRO | 6666 | |
---|---|---|---|
Address 1 | 77777 | Fax No | 666 |
Address 2 | 77777 | Telephone No | 6666 |
Consultant/s:
Status | Appointed |
---|
Contractor/s:
Status | Appointed |
---|
Progress:
Technical Progress | Delayed | ||
---|---|---|---|
Financial Progress | 61.81% | ||
Expected Completion Date | 12-2021 | ||
Created | 17-04-2018 | Updated | 25-09-2023 |