Project Information
Project Name | Expantion Of Power Systems | Status | Active |
---|---|---|---|
Region | Latin american & the caribbean countries | Country | Surinam |
Sector | Energy | Sub Sector | Exchanges |
Technical Details:
Project Objectives | The project aims at improvement of the welfare and living conditions of the population of Suriname and also the competitiveness of the domestic producers and exporters. This will be achieved by expanding and upgrading power generation, the transmission and distribution systems to meet the growing electricity demand. |
---|---|
Project Description | The project includes all necessary civil works, together with procurement, supply, and installation of electro-mechanical equipment to construct Paranam power station, and expansion and upgrading of the associated transmission network (Paranam power system). The project also includes all necessary civil works, together with procurement, supply, and installation of electromechanical equipment to expand the existing Clara Polder power station and expansion and upgrading of the associated transmission and distribution networks (Nickerie power system). In addition, the project will include the consultancy services, environmental and social impact studies, project management and financial audit. |
Estimated Cost | 152.00 Million Dollars |
Financing :
Co Financiers | |||
---|---|---|---|
Kuwait Fund Financing | |||
Type | Loan | No. | 1018 |
Amount | 5,000,000 KD | Effective Date |
Implementing Agency :
Agency | SURINAME NATIONAL ELECTRICITY COMPANY | uuuu | |
---|---|---|---|
Address 1 | uuuuuu | Fax No | uuuu |
Address 2 | uuuuuuu | Telephone No | uuuuu |
Consultant/s:
Status | Not Appointed |
---|
Contractor/s:
Status | Not Appointed |
---|
Progress:
Technical Progress | Delayed | ||
---|---|---|---|
Financial Progress | 0.00% | ||
Expected Completion Date | 12-2023 | ||
Created | 30-01-2019 | Updated | 08-09-2022 |