Sector | Sr. No. | Project Name | Loan Amount | Date of Agreement | Interest Rate | Loan Period (Years) | Grace Period (Years) | Grant Element |
---|---|---|---|---|---|---|---|---|
Water and Sewage | 1 | RECONQUISTA WATER SUPPLY (PHASE I) | 12.372 | 25-03-2014 | 3.00% | 25.08 | 5.08 | 50.07% |
Water and Sewage | 2 | GRAND TULUM AQUEDUCT IN SAN JUAN | 15.000 | 26-02-2015 | 3.00% | 27.58 | 7.58 | 54.14% |
Water and Sewage | 3 | LA PLATA WATER SUPPLY | 15.000 | 29-01-2018 | 3.00% | 24.00 | 4.00 | 47.99% |
Water and Sewage | 4 | CORDOBA'S MAIN AQUEDUCT PLAN | 15.000 | 11-12-2018 | 3.00% | 24.42 | 4.42 | 48.82% |
Water and Sewage | 5 | INTERPROVINCIAL AQUEDUCT SANTA FE - CORDOBA (PHASE 1- BLOCK A) | 15.200 | 22-05-2022 | 3.00% | 20.00 | 4.00 | 44.85% |
Total | 5 | 72.572 | ||||||
Transportation | 1 | PROVINCIAL ROAD NETWORK DEVELOPMENT | 10.572 | 27-06-1994 | 5.50% | 19.42 | 3.42 | 27.39% |
Total | 1 | 10.572 | ||||||
Grand Total | 6 | 83.144 | ||||||