Geographical And Sectorial Distribution Of Loans Up To 23-09-2023
Note: All Amounts are in Kuwaiti Dinar (Millions) (1 KD = US$3.40)
Sector | Sr. No. | Project Name | Loan Amount | Date of Agreement | Interest Rate | Loan Period (Years) | Grace Period (Years) | Grant Element |
---|---|---|---|---|---|---|---|---|
Social | 1 | THE RECONSTRUCTION OF HIGHER EDUCATION INSTITUTIONS PROJECT OF AJK | 14.300 | 04-01-2010 | 1.00% | 25.17 | 5.17 | 65.08% |
Total | 1 | 14.300 | ||||||
Agriculture | 1 | REPAIRS, MODIFICATIONS AND ADDITIONAL WORKS OF TARBELA DAM | 4.665 | 13-06-1979 | 3.50% | 24.42 | 4.42 | 45.20% |
Agriculture | 2 | SMALL IRRIGATION DEVELOPMENT SCHEMES IN BALUCHISTAN PROVINCE | 3.849 | 05-07-1982 | 1.50% | 31.08 | 6.08 | 66.42% |
Total | 2 | 8.514 | ||||||
Industry | 1 | FAUJI FERTLLIZER | 1.874 | 04-05-1981 | 4.00% | 19.58 | 4.58 | 38.62% |
Total | 1 | 1.874 | ||||||
Energy | 1 | GUDDU-KARACHI TRANSMISSION LINE | 12.950 | 10-04-1976 | 4.00% | 26.33 | 6.33 | 44.51% |
Energy | 2 | RURAL ELECTRIFICATION IN BALUCHISTAN PROVINCE | 3.999 | 14-07-1981 | 2.00% | 29.83 | 4.83 | 60.24% |
Energy | 3 | THE SECOND RURAL ELECTRIFICATION PROJECT IN BALUCHISTAN PROVINCE | 4.235 | 03-04-1994 | 2.00% | 37.42 | 17.42 | 72.71% |
Energy | 4 | SECONDARY TRANSMISSION LINES AND GRID STATIONS IN BALUCHISTAN PROVINCE | 9.298 | 07-01-1996 | 3.00% | 23.67 | 3.67 | 47.30% |
Energy | 5 | TRANSMISSION LINE FROM GHAZI BAROTHA HYDRO-ELECTRIC STATION PROJECT. | 7.487 | 29-09-1998 | 3.00% | 25.17 | 10.17 | 55.21% |
Energy | 6 | THE GOLEN-GOL-HYDROPOWER PROJECT | 11.000 | 21-03-2007 | 3.00% | 32.50 | 10.00 | 58.19% |
Energy | 7 | THE NEELUM - JHELUM HYDRO - POWER PROJECT | 12.000 | 25-11-2010 | 2.00% | 29.83 | 7.83 | 63.62% |
Energy | 8 | THE NEELUM - JHELUM HYDRO - POWER (SUPPLEMENTARY LOAN) | 9.500 | 26-02-2015 | 2.00% | 28.00 | 6.00 | 60.59% |
Energy | 9 | GOLEN-GOL HYDROPOWER (SUPPLEMENTARY LOAN) | 4.500 | 11-04-2018 | 3.00% | 0.00 | 0.00 | 0.00% |
Total | 9 | 74.969 | ||||||
Water and Sewage | 1 | QUETTA AND GADANI POTABLE WATER SUPPLY | 4.315 | 21-11-1981 | 1.50% | 31.50 | 6.50 | 67.13% |
Total | 1 | 4.315 | ||||||
Transportation | 1 | IMPROVEMENT OF THE FACILITIES AND OPERATIONS OF PAKISTAN RAILWAYS | 6.150 | 19-06-1977 | 4.00% | 17.75 | 2.75 | 34.73% |
Transportation | 2 | QUETTA NATURAL GAS PIPELINE | 6.364 | 22-06-1981 | 4.00% | 19.42 | 3.42 | 37.03% |
Transportation | 3 | Rehabilitation and improvement of track on Pakistan railway | 5.862 | 20-11-1990 | 4.50% | 17.33 | 3.33 | 32.13% |
Transportation | 4 | LYARI EXPRESSWAY. | 7.439 | 11-01-2005 | 2.50% | 27.67 | 9.67 | 60.14% |
Total | 4 | 25.816 | ||||||
Grand Total | 18 | 129.788 | ||||||